12 results for 2024 on the Lyon-Turin construction sites
The year ended with 12 good news for the single construction site of the cross-border section, which recorded a volume of works executed of around EUR 1 billion in the period 2024.
The official TELT website has changed: from August 2022, telt-sas.com becomes telt.eu. If you have any problems or need help, please contact us.
Home | Construction sites | Saint-Martin-la-Porte site
DECLINE AND BASE TUNNEL | 14,7 KM | WORK IN PROGRESS
After a first phase of activity between 2003 and 2010, the work is resumed from 2015 for the excavation of the second descent. From summer 2016 until September 2019, the TBM Federica dug 9 km in the axis and diameter of the south pipe of the base tunnel.
The construction of the 9 km-long geognostic tunnel, with the traditional 1.5 km-long section digged into the carboniferous fault, has made it possible to gain a better understanding of a geologically sensitive area in view of the final works.
The TBM boring this tunnel was designed to tackle certain specific geological characteristics of the area. Made in France, at the NFM Technologies facility in Creusot (Saône-et-Loire), it is fitted with an 11.26-metre-diameter head that holds 76 cutters and has a power of 5 Megawatt, the equivalent of 8 Formula 1 engines. The TBM’s average progress was 10 m per day.
TELT, while maintaining the leadership of the project, entrusted the work to a grouping of enterprises that includes six companies – three French and three Italian – specialising in public works, led by Spie Batignolles TPCI. Between the grouping of companies, the contractors and the subcontractors, the construction site employed 480 people.
8.700 m of tunnel to excavate with the TBM
+4.000 visitors until 2019
1.3 millions of rocks to be excavated
480 people employed during peak phases
The year ended with 12 good news for the single construction site of the cross-border section, which recorded a volume of works executed of around EUR 1 billion in the period 2024.
Work is progressing on the railway viaduct over the Arvan, the Chiomonte junction on the A32 and the new San Didero car and truck terminal.
A ministerial delegation was also present during the visit of the base tunnel works in Saint-Julien-Montdenis.
Excavations reached a total of 35.5 km, of which 13 of base tunnel.