The Lyon-Turin advances in underground and outdoors
Excavations reached a total of 35.5 km, of which 13 of base tunnel.
The official TELT website has changed: from August 2022, telt-sas.com becomes telt.eu. If you have any problems or need help, please contact us.
Excavation of the 3 km base tunnel between Saint-Julien-Montdenis and Saint-Martin-la-Porte
Home | The single construction site | Saint-Julien-Montdenis and Villargondran construction site
Excavation of the tunnel section between the French entrance portal in Saint-Julien-Montdenis and Saint-Martin-la-Porte. Work is also planned on the Villard-Clément platform between the artificial tunnel to the west (the cut-and-cover tunnel, already constructed) and the natural entrance of the tunnel into the mountain to the east. In addition, there will be communication branches every 333 metres between the two tunnels, technical rooms and niches for operation and safety.
The excavation of the base tunnel, started in December 2022 in Saint-Julien-Montdenis, continues towards Saint-Martin-la-Porte. The acoustic hangar, the conveyor belt and all the installations necessary for the smooth operation of the construction site were also built on this platform: offices, concrete plant, access tracks, etc.
3 km of base tunnel
70 months of work
300 people at work
2026 end of the excavation work
In July 2021, TELT awarded the contract to the group of companies composed of IMPLENIA Suisse (group head) / IMPLENIA France / NGE / ITINERA / RIZZANI de ECCHER. The project management is entrusted to the group composed of Egis (group head) / Ingérop / Alpina / Geodata. The value of the works is € 228 million.
Excavation in this section is carried out using the traditional method, i.e. with explosive or a jackhammer. These techniques are used in the most complex mountain sections, where it is not possible to use the TBM. Explosive excavation involves drilling holes in the rock face that are filled with explosives and then blasted. Once freed of debris, the face is consolidated with ribs and shotcrete. In some cases the calotte can be reinforced with steel bars. If the rock is less resistant and explosives cannot be used, a jackhammer is employed, consolidating the excavation with ribs and concrete.
In Saint-Julien-de-Montdenis, in the Villard Clément area, the cut-and-cover tunnel, the artificial tunnel that will be the French entrance to the base tunnel, was completed in November 2021.
Works to build the concrete ‘box’ under the A43 motorway and the RD1006 road started in 2019 and were completed in 32 months, as planned. The works were carried out by the group of companies led by Bouygues Travaux Public Regions France.
Consolidation works were carried out on the embankments of the Arc river to protect the Saint-Jean-de-Maurienne basin from floods, as well as to prepare the platform where the others railway and technical structures of the Lyon-Turin cross-border section will be located.
The land was raised by approximately 6 metres, using as backfill 25,000 tons of excavated material from the cut-and-cover tunnel and Saint-Martin-la-Porte construction site.
The work, which started at the end of 2018 for a value of approximately € 6.8 million, was carried out by a group of companies composed of Vinci Construction Terrassement (group head), Cofex GTM Travaux spéciaux, and TP Manno.
Excavations reached a total of 35.5 km, of which 13 of base tunnel.
The companies of the UXT consortium, led by Itinera, signed the Sustainability and Security Pacts with TELT.
The contract worth EUR 1 billion was awarded to the binational group of companies composed by Itinera (agent), Spie Batignolles and Ghella.
Excavation has started for the ventilation shafts of the Mont Cenis base tunnel.
By continuing to use the site, you agree to the use of cookies | Continuando ad utilizzare il sito, accetti l'uso di cookie | En continuant à utiliser le site, vous acceptez l'utilisation de cookies | PLUS
The cookie settings on this website are set to "allow cookies" to give you the best browsing experience possible. If you continue to use this website without changing your cookie settings or you click "Accept" below then you are consenting to this.